1/26/01 - Daily 1:15 pm all-hands meetings have continued under the leadership of Darrell Winfield  All days have been one and  1/2-shift, with work planned on 1/27 and 1/28   Lab work by PI teams continues beyond one shift as each team determines is appropriate

Nine of the experinent teams have been on-site at sometime during the week All racks and inlets are onboard  The Apel team arrived 1/22 and uploaded on 1/24  Each team continues final rack preparations as needed  Brune installed a measurement of opportunity for NO and NOx with no significant difficulty  The ICATS rack is ready for their go-no go flight test on 2/1 Ali Aknan and John Barrick will operate the Project Data System during that flight to insure ICATS provides the required functionalities  The ICATS Ground Operations Go/No Go Review was held 1/22 and was approved to continue preparations, even though it was not complete and flight worthy at that review as planned  The Sandholm lasers have been uploaded and NO appears near completion, while NO2 needs much more work, as expected  The Sachse DLH instrument will arrive 2/4 in plenty of time for installation prior to the first test flight  Eleven work tasks remain for various sheet metal and related work for the PIs and plane

DIAL completed significant modifications for its power handling black boxes during the week  DIAL was found to be continuing to trip the plane circuit breakers when it powered up(due to large initial spike)  Even though this was not new behavior, a Discrepancy Report was issued, requiring a fix Several fixes were required before the circuit breakers did not trip  The fix requires a special operational procedure(Mission Manager institutes time delay, which wll be acceptable for this mission, but additional fixes will be required for future missions to remove the man from the loop

Significant work remains to develop a transport plan for Blake's snakes The plan is shaping up to be a mix of routine courier, FEDEX, USAF cargo transport and C-130 transport  Care is being exercised to insure the PI believes that replacement of the courier approach to save money does not introduce unknown or unacceptable risk, and thereby dilute PI responsibility for success  The number of snakes available will not permit delays due to customs or lost cargo  Couriers under the control of the PI take multiple snakes aboard as excess baggage and personally deal with transport to and from the plane and customs  Replacement of the courier approach requires incresaed reliance on commercial transportation and puts the snakes in the hands of persons not familiar with, or especially committed to, the hardware

The Hazardous Materials CCB was completed with no problems

The site visit to Hong Kong and Okinawa was completed and a debrief conference call will be held 1/29  Okinawa support is committed for three visits  Hong Kong support of the aircraft is now committed as is PI laboratory workspace  It remains to be seen how we will deal with hazardous materials restrictions in this workspace

The Tech Brief (Mission summary and status of preparations for management and participants) will be held on 1/29  The all-up electrical power check will be on 1/30  Rollout, weight and balance will be on 1/31  The Engineering Check Flight will be on 2/1 in the morning and the ICATS Go-No Go test flight will be in the afternoon  A Pilot Prof Flight Test will be on 2/2

In summary, rack and inlets upload was completed as planned by 1/25; however, PIs continue to make final installations and adjustments  NO delays are anticipated for the test flights next week  Next week will begin flights of the plane with the result that PIs will have less time to work in the plane  There are no current problems which would appear to jeporidize on-time deployment