GTE PEM Tropics BP3-B INTEGRATION SCHEDULE |
Date | Event |
---|---|
January 11 - 15 | Ridley and Eisele racks to arrive at Wallops - upload Eisele rack by 1/15/99; Begin probe installation |
January 18 - 22 | Upload Clarke rack installation; Install Project
Data and Mission Manager rack; Upload Blake rack; Upload Talbot rack and install probes;Upload Bandy rack; |
January 25 - 29 | Upload Shetter Radiometers;Upload Ridley
rack; Upload Gregory/Anderson Rack; Upload Sachse
rack; Upload Heikes/O'Sullivan rack; install power bay cables |
February 1 | Complete upload of all racks |
February 5 | Modification of A/C power converter complete |
February 18 | Power up checkout/Hangar power to A/C |
March 1 | Functional Check Flight (NO PIs) & Engineering Check Flight (NO PIs) |
March 2 | Pilot Proficiency Flight (NO PIs) in AM. Power Up on Aircraft Power in PM |
March 3 | Mandatory Safety Briefing in AM. Test Flight #1 late afternoon. |
March 7 | Test Flight #2 |
March 10 | Transit to NASA Dryden Flight Research Center |
March 11 | Transit to Hilo, Hawaii |
March 13 | Transit to Christmas Island |
March 26 | Transit to Tahiti |
April 9 | Transit to Hilo, Hawaii |
April 10 | Transit to NASA Dryden Flight Research Center |
April 11 | Transit to NASA Wallops Flight Facility |
Aptil 12-17 | Off load |